We’re excited to announce that we will be moving the Open Hub Forum to https://community.blackduck.com/s/black-duck-open-hub. Beginning immediately, users can head over, register, get technical help and discuss issue pertinent to the Open Hub. Registered users can also subscribe to Open Hub announcements here.


On May 1, 2020, we will be freezing https://www.openhub.net/forums and users will not be able to create new discussions. If you have any questions and concerns, please email us at [email protected]

Estimated resources calculation

For the Project Cost calculator only, we use the Basic COCOMO model. This model considers only the total lines of code when estimating the years of effort required:

months = a * (KLOC) ^ b

a and b are arbitrary constants. Ohloh uses typical values of 2.4 and 1.05.

You can read more about COCOMO at wikipedia.

This is the only place on the website where we use COCOMO estimates. Elsewhere on the website (such as on the contributors pages), we measure the time more precisely by examining the actual source control logs.

Robin Luckey about 18 years ago